The true cost of the national fire safety recladding
project is 10 times higher than the Government’s allocated funding, according
to one of the largest specialist contractors in the Midlands. The government has
set aside £5bn for cladding remediation works but this falls woefully short of
the £50bn estimate Colmore Tang Construction believes is needed to make
every high-rise housing development compliant. The firm has priced remedial
projects on over 20 typical developments. It found the average cost of these
works to be around £4.65m for buildings above 18m and £2m for buildings between
11m and 18m, which they claim is fair reflection of typical costs across the
country. Read more on the Construction Enquirer website.
https://www.constructionenquirer.com/2021/04/20/true-cost-of-cladding-crisis-as-high-as-50bn/